| Repair and Renovation Capital Plan |
|
|
|
| Project |
Overall Priority |
Cost |
R&R Category |
| Howell Science - Replace HVAC System (Mold Problem) |
1 |
$9,407,266 |
MEP |
| Fletcher Music - Repair/Replace Storm Drain |
2 |
$87,641 |
LAND |
| Wright Circle Infrastructure and Fountain Repair |
3 |
$412,903 |
MEP |
| HSC- Replace Exhaust Fans at Brody Penthouse |
4 |
$465,869 |
MEP |
| Campus Sewer Repairs |
5 |
$400,646 |
MEP |
| Ward - Connection to Central Chilled Water Plant |
6 |
$302,989 |
MEP |
| Steam Plant Repairs |
7 |
$590,486 |
MEP |
| Austin Building Roof Replacemnt |
8 |
$220,536 |
ROOF |
| Professional Plaza - Replace Storm Water System |
9 |
$99,385 |
LAND |
| Reroof Mamie Jenkins Building |
10 |
$35,088 |
ROOF |
| Wright Circle - Mill and Repave |
11 |
$22,787 |
RWD |
| Rivers Building, DOI Renovations |
12 |
$26,970 |
FIRE |
| Various Academic Building HVAC Repairs |
13 |
$504,755 |
MEP |
| Steam Distribution System Steam/Condensate Expansion Joint Repairs |
14 |
$142,302 |
MEP |
| Steam Plant Fuel Oil Tank Replacement Phase I |
15 |
$134,170 |
MEP |
| Electrical Distribution Upgrades - Phase III |
16 |
$1,208,420 |
MEP |
| Founders Drive - Mill and Repave |
17 |
$35,954 |
RWD |
| Joyner Library Building Roof Replacement |
18 |
$452,477 |
ROOF |
| Rawl Building Roof Replacement |
19 |
$217,862 |
ROOF |
| Ormond Way - Repair and Repave |
20 |
$83,583 |
RWD |
| HSC Replace Roofs |
21 |
$1,063,424 |
ROOF |
| HSC Upgrades Elevators |
22 |
$1,238,591 |
MEP |
| Whichard Building Window Replacement |
23 |
$233,411 |
STRUCT |
| Steam Plant Floor/Roof Repairs |
24 |
$154,296 |
STRUCT |
| Wright Auditorium Ceiling Repair Project |
25 |
|
STRUCT |
| $62,221 |
| Upgrade Fire Alarm System to Addressible @ HSC |
26 |
$217,406 |
FIRE |
| HSC Replace Brody Roof |
27 |
$666,504 |
ROOF |
| Jenkins Art HVAC Repair |
28 |
$1,779,994 |
MEP |
| Brewster Elevator Repairs |
29 |
$200,794 |
MEP |
| Campus Backflow Preventor Installations |
30 |
$60,004 |
MEP |
| Various Campus Building Plumbing Repairs I |
31 |
$729,241 |
MEP |
| Howell East Elevator Repairs |
32 |
$155,290 |
MEP |
| Minges Coliseum - Repair & Repave Service Rd |
33 |
$27,341 |
RWD |
| Faculty Way - Repave |
34 |
$33,033 |
RWD |
| Mall - Repair Storm Drainage |
35 |
$156,503 |
LAND |
| HSC Brody Masonry Repairs - Phase II |
36 |
$403,753 |
STRUCT |
| HSC Upgrade Two Classrooms in Brody |
37 |
$248,464 |
UAB |
| Jenkins Art Exterior Envelope Project |
38 |
$702,425 |
STRUCT |
| Graham Building Window Replacement Project |
39 |
$138,767 |
STRUCT |
| Ragsdale Building Roof Replacement |
40 |
$234,306 |
ROOF |
| HSC HVAC Upgrades |
41 |
$781,418 |
MEP |
| Upgrade Chillers @ HSC |
42 |
$770,237 |
MEP |
| Steam Plant-Repave Roadway & Service Area |
43 |
$23,617 |
RWD |
| Willis Building - Repave Service Drive |
44 |
$41,853 |
RWD |
| Spilman/Bate Buildings - Storm Drain Replacement |
45 |
$177,787 |
LAND |
| Various Campus Buildings Sprinkler System Installations |
46 |
$1,035,511 |
FIRE |
| Howell Science North/South Glass Piping Repairs |
47 |
$555,004 |
MEP |
| Mall Area Lighting Improvement |
48 |
$361,825 |
MEP |
| Graham Building, DOI Renovations |
49 |
$117,469 |
FIRE |
| Speight HVAC Repairs |
50 |
$953,568 |
MEP |
| Spilman Building Roof Replacement |
51 |
$107,461 |
ROOF |
| Messick Theatre Arts Building Roof Renovation & Replacement Project |
52 |
$156,046 |
ROOF |
| Messick Theatre Arts Building Window Replacement Project |
53 |
$166,222 |
STRUCT |
| Wright/Ragsdale Area-Replace Storm Drain |
54 |
$60,097 |
LAND |
| Duncan Court - Repave |
55 |
$10,853 |
RWD |
| Dowell Way - Repave |
56 |
$8,179 |
RWD |
| HSC Renovate Brody Auditorium |
57 |
$559,043 |
UAB |
| HSC Security Upgrades |
58 |
$173,925 |
UAB |
| Graham Electrical Repairs |
59 |
$84,291 |
MEP |
| Austin/McGinnis Electrical Repairs |
60 |
$204,660 |
MEP |
| Various Campus Buildings Plumbing Repairs II |
61 |
$100,131 |
MEP |
| Various Campus Buildings Electrical Repair |
62 |
$449,440 |
MEP |
| Steam Plant Diesel Tank/Fuel Oil Lines Replacement |
63 |
$150,320 |
MEP |
| HSC Upgrade No. 1 Boiler |
64 |
$347,255 |
MEP |
| HSC Electrical Upgrades |
65 |
$549,308 |
MEP |
| Spilman Building, DOI Renovations |
66 |
$157,024 |
|
| FIRE |
| Bloxton Building Window Replacement Project |
67 |
$39,556 |
STRUCT |
| Brewster - Correct Structural Defiencies |
68 |
$1,351,964 |
STRUCT |
| Brewster - Replace Storm Drain |
69 |
$40,782 |
LAND |
| HSC Grounds Improvements |
70 |
$307,993 |
LAND |
| Steam Plant Fuel Oil Tank Replacement Phase II |
71 |
$325,525 |
MEP |
| Steam Distribution System New Steam Line |
72 |
$4,518,493 |
MEP |
| Steam Tunnel Steam/Condensate Piping Repairs |
73 |
$990,252 |
MEP |
| Wright/Wright Annex HVAC Repairs |
74 |
$4,767,840 |
MEP |
| Steam Distribution Center Condensate Tanks/Sump Repairs |
75 |
$301,883 |
MEP |
| Laupus Lake-Repair and Replace Path around Lake |
76 |
$18,719 |
LAND |
| Tyler/Belk Residence Halls - Repave Connecting Road |
77 |
$11,088 |
RWD |
| HSC Pavement Repair and Replacement |
78 |
$262,750 |
RWD |
| HSC ADA/DOI Upgrades |
79 |
$150,320 |
FIRE |
| HSC Upgrade Ultrapure Water System |
80 |
$131,686 |
MEP |
| Ragsdale Hall, DOI Renovations |
81 |
$317,645 |
FIRE |
| Howell - Correct Structural Deficiencies |
82 |
$815,790 |
STRUCT |
| Eller Building Window Replacement |
83 |
$31,816 |
STRUCT |
| Eller, International, Taylor Slaughter House DOI Renovations |
84 |
$72,279 |
FIRE |
| Rawl HVAC Repairs |
85 |
$2,542,848 |
MEP |
| Spilman HVAC Repairs |
86 |
$1,080,710 |
MEP |
| Joyner West HVAC Repairs |
87 |
$762,854 |
MEP |
| Replacement Steam & Condensate Lines from Bate to Rivers |
88 |
$2,676,400 |
MEP |
| Trustees Way and Chancellors Way - Repave |
89 |
$46,673 |
RWD |
| Beckwith Drive - Repave |
90 |
$11,688 |
RWD |
| Ficklen Drive - Partial Repave |
91 |
$19,410 |
RWD |
| HSC Upgrade West Academic Building |
92 |
$541,007 |
UAB |
| HSC Upgrades Academic Buildings |
93 |
$498,791 |
UAB |
| Emergency Generator Upgrades @ HSC |
94 |
$621,159 |
MEP |
| Messick Theatre Arts Center, Correct DOI Deficiencies |
95 |
$253,433 |
FIRE |
| Fletcher Music - Correct Structurual Deficiencies |
96 |
$531,849 |
STRUCT |
| Austin - Correct Structual Deficiencies |
97 |
$1,174,680 |
STRUCT |
| Central Chiller Plant - Chiller Addition Phase I |
98 |
$1,292,275 |
MEP |
| Brewster - Connection to Central Chilled Water Plant |
99 |
$215,347 |
|
| MEP |
| Fletcher Music Center, DOI Renovations |
100 |
$66,286 |
FIRE |
| Austin - Connect to Central CHW Loop |
101 |
$215,347 |
MEP |
| Graham Building Elevator Addition |
102 |
$774,124 |
ADA |
| ="Alumni Drive - Remove & Replace with Pedestrian Sidewalk/Landscaping ">Alumni Drive - Remove & Replace with Pedestrian Sidewalk/Landscaping |
103 |
$123,199 |
RWD |
| Cotton Hall - Replace Storm Drain on South Side |
104 |
$11,926 |
LAND |
| 10th Street North - Pedestrian Crossing |
105 |
$123,601 |
LAND |
| Speight - Correct Structural Deficiencies |
106 |
$497,257 |
STRUCT |
| Rawl - Correct Structural Deficiencies |
107 |
$998,838 |
STRUCT |
| Bate - Correct Structural Deficiencies |
108 |
$1,484,565 |
STRUCT |
| Spillman Building Elevator Addition |
109 |
$500,808 |
ADA |
| Sewer Cross Connection |
110 |
$120,194 |
MEP |
| Speight - Connect to Central CHW Loop |
111 |
$215,347 |
MEP |
| Central Chiller Plant - Chiller Addition - Phase II |
112 |
$3,846,396 |
|
| MEP |
| Electronic Door Access Project |
113 |
$648,426 |
UAB |
| Leary Court - Repave |
114 |
$7,579 |
RWD |
| Replace CW Coils @ Brody AHU 4, 5, & 6 |
115 |
$496,927 |
MEP |
| McGinnis - Connect to Central CHW Loop |
116 |
$215,347 |
MEP |
| Rawl - Connect to Central CHW Loop |
117 |
$215,347 |
MEP |
| Wright - Connect to Central CHW Loop |
118 |
$215,347 |
MEP |
| Graham - Connect to Central CHW Loop |
119 |
$215,347 |
MEP |
| Ragsdale Building Elevator Addition |
120 |
$500,808 |
ADA |
| Maintenance Warehouse - Improve Parking Lots, Walks and Drives |
121 |
$88,169 |
RWD |
| Replace Heat Wheels at Brody Penthouse, AC-1 and AC-7 |
122 |
$559,043 |
MEP |
| Fletcher Music New Steam Supply |
123 |
$579,685 |
MEP |
| Spillman - Connect to Central CHW Loop |
124 |
$215,347 |
MEP |
| Whichard Building Elevator Addition |
125 |
$500,808 |
ADA |
| Whichard - Connect to Central CHW Loop |
126 |
$215,347 |
MEP |
| Memorial Gym Roof Renovation |
127 |
$58,130 |
ROOF |
|
|
|
|
| |
|
|
|

|
|