Construction for the next 6 Months
Contact Project Managers below at 252-328-6858
Athletic Facilities Additions & Improvements Phase 1
Phase 1 Project is the construction of a new 1000 seat ladies softball facility including grand stands, press box, concessions, toilets, a field and other support elements. The facility will be constructed to the north of the existing facility. The Phase 1 Softball project will have two parts. Part "A" will be an early site package. Part "B" will be the softball facility and final associated site work.
Bid "B" Expected: December 2009 Total Project Estimate: $4,800,000
Project Manager: Robert Brown Construction Manager at Risk: TA Loving Company
Fletcher Residence Hall Bathroom Renovations
Replace showers and shower pans, renovate showers, lavatories and toilets for Handicap accessibility. General update of toilet rooms.
Bid Expected: January 2010 Total Project Estimate: $1,111,175
Project Manager: Nick McKinley
Tyler Residence Hall Renovation
91,095 sf of general renovation of a 9-story residence hall including new fire suppression system; replacing resident room entry doors; upgrading interior finishes; reconfiguring resident bathrooms; abating lead and asbestos; re-cladding the building exterior with masonry-faced precast panels; and new accessible entry. Construction activity limited to two 85 day summer periods, the first in 2010 and the second in 2011.
Bid Expected: Dec 2009 Total Project Estimate: 11,000,000 Project Manager: Eugene Tashiro
Construction Manager @ Risk: Barnhill Contracting
Howell Science Area Sewer Improvements
Replace Sanitary Sewer line extending from the rear of Howell Science Building to 10th Street manhole. Design under contract to Rivers & Associates.
Bid Expected: December 2009 Total Project Estimate: $80,000
Project Manager: Eugene Tashiro
Aycock Residence Door Replacement
Replace suite doors with Rated Doors.
Bid: November 17, 2009 Total Project Estimate: $642,007 Project Manager: Gerry Gable
Fletcher-Garrett Fire Sprinkler
Install new fire Sprinkler system in two residence halls.
Bid Expected: December 2009 Total Project Estimate: $2,200,000
Project Manager: Gerry Gable
Coastal Studies Institute
Project is the construction of a 90,000 square foot complex on 40 acres of land in Manteo, NC. The project will have an academic/administrative area, laboratory area, research plots, and residential facilities. Project will be LEED certified.
Bid Expected: August 2010 Total Project Estimate: $28,909,000
Project Manager: Gina Shoemaker
Construction Manager at Risk: Whiting Turner
Aycock Residence Hall Fire Alarm
This project replaces the existing analog fire alarm system in its entirety with a state-of-the-art addressable fire alarm system throughout the entire building.
Bid Expected: November 2009 Total Project Estimate: $338,896 Project Manager: Nick McKinley
East End Zone Seating Addition
East Carolina University is constructing a 7,000 seat expansion to Dowdy-Ficklen Stadium. The new seating capacity will enclose the East End Zone with bench seating and a two-tiered level of viewing spaces that comply with ADA requirements. New concessions and toilet facilities will be constructed beneath the seating area. The expansion will also include a new, state of the art, video scoreboard.
Bid Expected: December 2009 Total Project Estimate: $18,000,000
Project Manager: Gina Shoemaker Construction Manager at Risk: T.A. Loving
ECU School of Dentistry
This is the first phase of the construction of the new School of Dentistry, approximately 185,184 gross square feet, and includes the site, steel, concrete, and core of the building. The second phase will include the remainder of the work.
Bid Expected for Phase 1: January 2010 Total Project Estimate: $21,000,000
Project Manager: Michael Talton Construction Manager at Risk: Balfour Beatty Construction