February 10, 2005 Update
Schedule
Original Contract Completion Date = 01/24/2006
Approved Contract Duration Changes = -0-
Present Contract Completion Date = 01/24/2006
CM @Risk Requested Duration Changes (under evaluation) = 28 Days
CM @Risk Present Scheduled Completion Date = 02/28/2006
Status of Work
Building foundations are complete. Erection of masonry foundation walls and backfilling at the completed foundations will complete within the next two weeks. Steel erection on the Library section is complete, and erection in the Allied Health section is 60% complete. The installation of the concrete floor slabs will be completed in the Library section on this Friday, and the first pour in the Allied Health section is schedule for Monday. Mechanical, electrical and plumbing contractors have been installing hangers prior to the fireproofing of the steel structure. Four of the masonry stair towers are being worked. Grading of the southwest parking lot is almost complete. Final grading of the north parking lot is completing.
Work Next 30 Days
Structural steel erection in the Allied Health area will be completed and will be starting in the Nursing section. Concrete floor slab pours will continue in the Allied Health section. Installation of sprayed on fireproofing will start in the library section, as well as MEP rough-ins. Exterior masonry work will start on the Library section. Curb and gutter will be installed in the southwest parking lot. Grading of the northeast parking extension will occur. The base paving coarse will be installed on the north parking lot.
Issues
Presently the work is sixteen days behind the CM@Risk construction schedule due to manpower issues with the foundation sub-contractor. The CM@Risk has started implementing plans with the steel erection and concrete slab pours that should start showing results this month.
Review of the draft Audio Visual Equipment Design will be completing next week, and comments forwarded to the designer. Review meetings will then be scheduled to discuss the comments and determine decisions, so the final bid package can be prepared for review in early March.
Furniture samples are to be delivered the week of February 21-25 and will be set up for review and comment.
The designer should be preparing the initial color selections for review in March.