May 12, 2005 Update

Schedule

Original Contract Completion Date = 01/24/2006
Approved Contract Duration Changes =  -0-
Present Contract Completion Date =  01/24/2006
CM @Risk Requested Duration Changes (under evaluation) = 28 Days
CM @Risk Present Scheduled Completion Date = 03/20/2006

Status of Work
Library Section - Installation of the bowstring trusses is complete and installation of roof panels will complete shortly.  Installation of the pre-cast concrete panels at the penthouse is 60% complete.  Installation of fireproofing of the steel structure is mostly completed.  Installation of concrete block is approximately 95% complete.  Brick installation has started on the east and south elevations.  Installation of metal stud walls is completed in most of the section.  MEP trades are continuing installation of ductwork, plumbing lines and electrical conduits throughout the building. In wall electrical and data conduit work is ongoing.

Allied Health Section - Installation of roof panels is mostly completed.  Installation of fireproofing of the steel structure is 85% complete.  Installation of concrete block is 80% complete.  Installation of metal stud walls is 60% complete.  MEP trades are continuing installation of ductwork, plumbing lines and electrical conduits throughout the building.  In wall electrical and data conduit work is ongoing.

Nursing Section - Installation of concrete floor slabs are 95% complete.  Installation of roof panels is mostly completed.  Installation of concrete block has started.  Layout of metal stud walls has started.

Work Next 30 Days
Library Section - Installation of pre-cast concrete panels will be completed.  Installation of roofing will be started.  Installation of concrete block will be completed and placement of brick will be ongoing.  Installation of window should be started.  Installation of ductwork, plumbing lines and electrical conduits will continue both above ceilings and in walls.  Electrical power line installation will be started.

Allied Health Section - Installation of pre-cast concrete panels should be ongoing.  Installation of fire proofing, concrete block, and metal stud walls should be completed.  MEP trades will continue installation of ductwork, plumbing lines and electrical conduits throughout the building.  In wall electrical and data conduit work will be ongoing.

Nursing Section - Installation of concrete floor slabs will be completed.  Installation of concrete block and metal stud walls will be ongoing. Installation of fireproofing should be completed.  MEP trade contractors will begin installation of ductwork, plumbing lines and electrical conduits.

Issues
Presently the work is 27 days behind the CM@Risk construction schedule.  Some issues have arisen with delivery and installation of the pre-cast concrete panels, but the issue is being work through and the time is expected to be made back up.

 Audio Visual Equipment Design - The revised pricing estimate was still $282,000 over the original budget, so program elements will have to be identified for alternate bids.  The user groups have been asked to identify priorities of needs in order to match up with the levels of funding that might actually be received.

The carpet quality/selection issue should be resolved shortly, so the designer should be have the initial color selections for review before the end of the month.

Final selection boards for the furniture to be presented after selection of interior building color selections. The user groups have been asked to identify priorities of needs in order to match up with the levels of funding that might actually be received. 
 


 