June 9, 2005 Update

Schedule
Original Contract Completion Date =  01/24/2006
Approved Contract Duration Changes = -0-
Present Contract Completion Date = 01/24/2006
CM @Risk Requested Duration Changes (under evaluation) = 28 Days
CM @Risk Present Scheduled Completion Date = 03/6/2006

Status of Work
Library Section - Installation of the bowstring trusses and installation of roof panels will complete shortly.  Installation of the pre-cast concrete panels at the penthouse is complete.  Installation of fireproofing of the steel structure is completed.  Installation of concrete block is complete.  Installation of roofing has started.  Brick installation is 30% complete.  Installation of metal stud walls is completed in most of the section.  MEP trades are continuing installation of ductwork, plumbing lines and electrical conduits throughout the building. In wall electrical and data conduit work is ongoing.

Allied Health Section - Installation of roof panels is completed.  Installation of fireproofing of the steel structure is complete.  Installation of concrete block is 95% complete.  Installation of metal stud walls is 90% complete.  MEP trades are continuing installation of ductwork, plumbing lines and electrical conduits throughout the building.  In wall electrical and data conduit work is ongoing.

Nursing Section - Installation of concrete floor slabs is complete.  Installation of roof panels is mostly completed.  Installation of concrete block is 40% complete.  Layout of metal stud walls is ongoing and installation of stud walls has started.  MEP trades have started installation of ductwork, plumbing lines and electrical conduits throughout the building.  In wall electrical and data conduit work is ongoing.

Work Next 30 Days
Library Section - Installation of roofing will be ongoing.  Placement of brick will be ongoing.  Installation of windows should be started.  Installation of ductwork, plumbing lines and electrical conduits will continue both above ceilings and in walls will continue.  Electrical power line installation will be started.  Installation of drywall should be started.

Allied Health Section - Installation of pre-cast concrete panels should be completed.  Installation of roofing should be started. Installation of metal stud walls will be completed.  MEP trades will continue installation of ductwork, plumbing lines and electrical conduits throughout the building.  In wall electrical and data conduit work will be ongoing.

Nursing Section - Installation of concrete block and metal stud walls should be completed. Installation of fireproofing will be completed.  MEP trade contractors will begin installation of ductwork, plumbing lines and electrical conduits.  In wall electrical and data conduit work will be ongoing.

Issues
Presently the work is 13 days behind the CM@Risk construction schedule.  Time has been made up through the use of alternative fireproofing materials in the mechanical penthouses which is allowing roofing to be started sooner.

Audio Visual Equipment Design - The revised pricing estimate was still $282,000 over the original budget, so program elements will have to be identified for alternate bids.  The user groups have been asked to identify priorities of needs in order to match up with the levels of funding that might actually be received.  Awaiting resolution of funding.

The carpet quality/selection issue should be resolved shortly, so the designer should be have the initial color selections for review before the end of the month. Contractor has had difficulty getting the pricing from the supplier.

Final selection boards for the furniture to be presented after selection of interior building color selections. The user groups have been asked to identify priorities of needs in order to match up with the levels of funding that might actually be received.  Awaiting resolution of funding.
 


 