Purchase of property:  $2,444,160.13

Phase I:  $6,076,000 Development Costs

Size of buildings at the NP

Field house:            5,456 SF with picnic shelter
2,600 SF of covered picnic shelter
Shingled building with concrete floors and split faced brick exterior walls

Maintenance building:  1,860 SF
                        Metal roof building with concrete service bays and tile office/common areas

Open Air Storage building:  2,400 SF
                        Metal roof with concrete floors

Total Acreage at NP for Phase I:  58.6 acres

Fields:                  Eight lighted multi-use sport fields. Four fields sized for rugby (225’ x 465’) and 4 fields sized for soccer (225’ x 330’)

Acreage of mowing:  50 acres

Acreage of playing fields:  23 acres

Ponds:  6 acres used for irrigation. Well replenished.

Parking Lot:  3 acres, 417 spaces

Plantings:  358 trees, 350 shrubs, and 728 daylilies'

General contractor:  Burney and Burney

Subcontractors:

Sports Fields:  Nolan Thomas & Company

Sports Fields Lighting: Wheeler

Landscape and Nursery:  Redmill landscape & Irrigation

Asphalt and Sidewalk:  Home Run Construction

Fencing:  Frye Fencing Company

Signs:  AOA Signs

Rock Hauling:  Mebane Trucking

Water/Sewer/curb and gutter paving:  Harrelson & Smith Contracting

Electric:  Wheeler Electric

HVAC:  Eneco East, Inc.

Plumbing:  Josh Bradshaw Plumbing

Site Surveyor:  HC Harris, Jr. Engineering & Surveying